Aba Power restored to National Grid after 10 days

Electricity pylons

The Aba Power management noted that this is the first time in Nigeria’s history that an entire area serviced by an electricity distribution company has been cut off from the National Grid.

By Jeffrey Agbo

The management of Aba Power on Monday announced it has been restored to the National Grid after 10 days of disconnection.

Explaining what led to the disconnection, the management said in a statement: “We would like to inform the wonderful people and government of Abia State and, indeed, all Nigerians that Aba Power was reconnected to the national transmission grid at 00.00 hours today, after 10 days of disconnection over payment to Federal Government agencies in the power sector.

“On April 19, 2023, the Market Operator, a unit of the  Transmission Company of Nigeria (TCN) wrote us a notice giving us 30 working days to clear the debt with it, and served us the letter the next day.  The same day, the Market Operator wrote to the TCN asking it to cut us off immediately from the national grid. The Market Operator complied. 

“Despite the unfavourable operating environment in the country which has gravely impacted our customers’ ability to pay their bills, Aba Power paid N120m to the Market Operator last Friday, so as to reconnect it to the grid immediately. Aba Power took effective control of the Aba Ringfence servicing nine local government areas in Abia State only last September, yet it has paid the N440m to Federal Government agencies in the power sector in the last six months.”

The Aba Power management noted that this is the first time in Nigeria’s history that an entire area serviced by an electricity distribution company has been cut off from the National Grid.

READ ALSO:

Aba Power warns customers against extortion as demand for prepaid meters soars

“In the case of other DisCos, not more than feeders would be put out for two or three days, despite owing billions of naira,” it continued.

“While the blackout in the Aba Ringfence lasted for more than one week which caused us tremendous revenue and equipment losses, Nigerians from all parts of the country demonstrated not just an uncanny understanding and patience but also amazing solidarity with us. They included top government officials, trade groups, business leaders, community leaders, security officers and others too many to mention here, seeking how they could be of help.

“We cannot thank them enough for their stupendous confidence in us and unflinching commitment to the common good. But we can pledge to continue to work harder to provide reliable, quality and affordable power to all nine local government areas in Abia State we serve.”

The management added that in order to serve its customers better, individuals and communities should guard power infrastructure in their localities and report any act of vandalism.

It said, “We also need electricity consumers to pay their bills as and when due. When we generate revenue from customers who pay for power consumed, we will be able to discharge our obligations to not just electricity providers like the Niger Delta Power Holding Company Ltd but also government agencies like the Transmission Company of Nigeria. As a result, we will be able to avoid experiences like cutting off people and businesses in the Aba Ring fence from the national grid.

“A situation where only 40 per cent of businesses and individuals in the Aba Ringfence pay what they should is unacceptable. Many electricity consumers bluntly refuse to pay for power consumed; some engage in meter bypassing; some others in other grave malpractices which can only make constant, quality and affordable power supply very difficult.”